Preparing for national-security questions in public procurement

Cabinet Office guidance asks central government buyers to examine supply risks in four sectors. The July amendment changed a contact address. The June guidance is where suppliers should look for the policy and how buyers are expected to use it.

Cabinet OfficeFirst published by source Source updated TenderSNAP published

Daylight across seating and woodwork in a civic chamber

Which procurements the policy asks buyers to examine

PPN 025 names shipbuilding, steel, artificial intelligence and energy infrastructure. It directs central government departments, their executive agencies and non-departmental public bodies to identify relevant work in their pipelines and engage the designated sector leads early. The note also encourages relevant private utilities to consider the energy-infrastructure guidance.

The supporting guidance asks buyers to consider how important a service or capability is, where supply is concentrated and what would happen if supply were interrupted. Those questions can reach beyond a bidder’s own facilities. An energy infrastructure supplier, for example, may depend on a specialist component with few credible replacements. The useful evidence is the dependency and the approach to maintaining continuity if it fails.

The note assigns sector leads so departments can discuss their intended approach before going to market. This can make early market engagement valuable for specialist firms with evidence about capacity, qualification lead times or substitute components. Give buyers enough detail to understand constraints, using whatever channel they have specified for information that needs protection.

PPN 025 policy text · National security implementation guidance

A sector label does not make a purchase exempt

The note discusses the national security exemption in Schedule 2 to the Procurement Act 2023. The supporting guidance says the authority needs a case-specific justification and must act consistently with relevant trade obligations. It also describes other options, including supplier assurance and contractual safeguards. Bidders should check the notice and documents for the route and conditions the authority actually chose.

The exemption is a decision about the procurement route. Supplier exclusions, debarment checks and individual security requirements are separate questions. The guidance says authorities should still check the debarment list when applying the exemption. In practical terms, answer the assurance questions you have been asked using the relevant evidence. Ask the authority through its clarification process if the scope of a requirement is ambiguous.

National security implementation guidance

Explain how you would keep supplying

Start by identifying the parts of delivery that are hard to replace. For each significant dependency, know the responsible team, the relevant subcontractor or supplier and the effect of a failure. Where a second source is proposed, explain what it would take to qualify it and how quickly you could switch. A substitute that needs approval or testing is a contingency, not immediate capacity.

Keep the account of your supply chain current. Separate evidence that can be included in an ordinary bid from material that needs a secure channel or approval to disclose. Bid managers should ask technical or security colleagues to review the contractual promises before submission. For a specialist subcontractor, it is worth confirming with the lead bidder which details it needs, who will see them and how they will be updated when delivery plans change.

Assign ownership of security evidence