How to prepare evidence for the steel transparency measure
The July revision to PPN 022 added an award-stage transparency measure for certain steel procurements starting from October 2026. Main contractors and their suppliers need a reliable way to report where steel is expected to come from.

Check the size of the project, not just your package
The Cabinet Office says the additional measure applies to relevant steel procurements commencing from 1 October 2026 that form part of a project or programme worth £10 million or more, or expected to require more than 500 tonnes of steel. The test concerns the project or programme. A small subcontract can contribute steel to a project that meets one of those tests.
The FAQs cover steel bought directly and steel procured within the supply chain. A component supplier or fabricator can therefore hold information that a main contractor needs. Check the scope of the buyer’s procurement and the relevant contract terms rather than assuming that the presence of steel alone triggers the additional measure. The policy note contains other actions and the FAQs distinguish their scope from the new reporting requirement.
Steel procurement FAQs · Guidance on recording steel origin
What the buyer reports at award
For qualifying awards, the guidance asks the buyer to record expected use of UK-produced steel in the Contract Details Notice. It gives four reporting outcomes: all UK-produced, all non-UK-produced, mixed or unknown. For cases involving non-UK steel or unknown origin, the guidance explains when to record a rationale. An unappointed subcontractor is one example of why some information might be unavailable at award.
That field describes what the buyer knows at that stage. Procurement teams should read it alongside the other directions in the guidance and the buyer’s own documents. If a bid uses a mixture of products, show which elements are confirmed and which are subject to supplier selection. An overall percentage on its own can make it difficult for the prime contractor to reproduce the estimate when assumptions change.
Guidance on recording steel origin
Make the evidence follow the steel package
Ask estimators and subcontractors to record the package, expected tonnage, proposed supplier and the evidence behind the claimed origin. Mark an estimate as provisional if the purchasing decision has yet to be made. For example, a main contractor could record the proposed source for reinforcement while leaving a separate cladding package unresolved, with a date for the subcontractor to confirm it.
Keep the award estimate separate from the records needed for actuals reporting. The guidance describes recording origin against the relevant inspection certificate and checking whether it identifies where the steel was melted and poured. A delivery note may tell you where material was dispatched. Check what it actually proves before treating it as origin evidence. Agree who will collect the records and how changes will be reported while the contract is running.
For actuals, the guidance says contractors are not expected to investigate further if their test certificates do not state the melt and pour location. That distinction matters when defining what a fabricator should record. Capture the certificate reference and record exactly what it says rather than trying to fill gaps after delivery.